Customer-supplied material sounds like a win: the client buys the stock, you just cut or print it. In practice, it often introduces hidden risk that eats margin and schedule. The material shows up late, out of spec, without certs, or damaged in transit. When the job goes sideways, the shop usually owns the delay.
Why Customer-Supplied Material Changes the Quote
Standard quotes assume you control the supply chain. You know the lead time, the grade, the heat lot, and the surface condition. When the customer supplies the material, those variables move outside your control but stay inside your responsibility. The quote must reflect that shift.
Verify Before You Commit
Ask for the mill certificate, heat number, and dimensional inspection report before you finalize the quote. If the customer cannot provide them, price the job as if you are sourcing the material yourself — including your markup and lead time. That protects you if the stock turns out to be wrong and you have to procure replacement.
Define Acceptance Criteria in Writing
Specify exactly what condition the material must arrive in: dimensions, surface finish, straightness, hardness range, and packaging requirements. State that material failing inspection will be rejected at the customer’s expense and the schedule will reset. Put this in the quote terms and the purchase order.
Build a Receiving and Inspection Buffer
Add a line item for receiving inspection: unloading, visual check, dimensional sampling, and cert review. Even a half-hour of CMM time on a critical feature prevents days of rework later. If the job is high-value or tight-tolerance, budget a full first-article on the raw stock before you touch a tool.
Clarify Liability for Damage and Yield Loss
Who pays if the bar cracks during machining? Who owns the scrap if the powder lot has high oxygen content? The quote should state that the customer retains risk of loss until the material passes your receiving inspection, and that yield loss due to material defects is not covered by your warranty.
Set a Firm Delivery Window
Quote a start date that triggers only after material passes inspection, not when the PO is signed. If the stock arrives late, the schedule slides automatically. This prevents the classic trap where you hold machine time open for material that never shows.
When to Say No
Some jobs are not worth the risk: exotic alloys with no traceability, high-volume runs where a bad lot kills the schedule, or customers who refuse written acceptance terms. It is better to decline or insist on sourcing the material yourself than to absorb a loss you did not create.
Quoting customer-supplied material accurately means pricing the uncertainty, not just the machining. Solvi helps digital manufacturers build quotes that capture these variables — inspection time, schedule contingencies, and liability terms — so the shop stays protected and profitable.